  1. Ideation Process (IDP):

UNTIL MID MAY

DONE

a) New Ideas are discussed

DONE

b) Decision of the editors if they are going to implement the idea is taken


DONE

c) What needs to be done is clear, outlined and planned

DONE

2. Implementation Process (IMP): 

UNTIL END JUNE

DONE

a) Editors enter their changes in the internal database 


DONE

3. Release Process (REP): 

PLANNED UNTIL END 2023


a) Work of the review team

SEPT - NOV 2023

DONE

b) Fine-tuning in English & translation into German, Spanish and Italian.

NOV 2023

IN PREPARATION

c) Creation of the JSON in English, so that all online tools have the same content as in the manual. (esp. eCalculator by Michael and Wordpress reporting template by Roland)

SEPT 2023

IN PREPARATION

d) Layout for print

NOV 2023


e) Publication of layouted versions on the web (websites?)

JAN 2024


f) Webbinars for consultants / audit (sessions for Q&A)

JAN. 2024

IN PREPARATION

Matrix 6.0

Work on 6.0 is scheduled to begin in early 2024.

Further Improvements to the matrix are planned, including major changes to the scoring system and an CSRD alignment.

Currently, we are awaiting the strategic decision (planned for mid-March). The team also needs new members and resources in order to be able to handle the large workload.

********


CSRD 

The Working Group CSRD/ESRS is currently working on the combination/linking of int. reporting standards, such as ESRS/CSRD, NFI 2013/34, Taxonomy, CSDDD and ECG.

...

  • Focus on Int. level / EU, instead of national implementation or third countries
  • Basis Matrix 5.0
  • Focus CSRD/ESRS, collaborate with A-Team & B-Team to combine ECG 5.0 & Taxonomy, CSDDD 
  • Work in Progress: all ESRS-documents are still drafts
  • VSME/LSME standards cannot be scheduled until drafts are available



Info
titleupdate 11/2023

Update 11/2023

Working on Scenarios & Framework to support the strategic decision by FMC.


Decision by MDT (Oct 2023)

The CSRD group is assigned to design and propose a framework to be presented to the EMT and the movement after presentation to MDT.

The CSRD-Group expresses preference and recommends one of the scenarios to EMT in the name of the MDT. 


planned Deliverables by 12/2023 | stopped due to lack of financing

...

Possibilities for Feedback 

How to give feedback

  • In principle: we ask for feedback that is as concrete as possible and also names the subject area/chapter+section so that it can be assigned to the editor. If there are requests for changes, it would also be helpful to have suggestions for improvement. 
      • Email: bilanz@ecogood.org
      • Online meetings are convened as needed on specific topics and issues. Experts with expertise in the various topics can contact the MET and will be invited to the meetings.
      • Exchange meeting for auditors/editors/consultants: DACH network meeting: may 16th-18th 2024 - international network meeting planned for autumn 2024

...